EA-07-199 · ORDER · Issued 2007-08-15 · Reactor Licensees
Action
EA Number
EA-07-199
Licensee
ORDER
Category
Reactor Licensees
Action type
ORDER
Date issued
2007-08-15
Description
On August 15, 2007, a Confirmatory Order (Effective Immediately) was issued to FirstEnergy Nuclear Operating Company (FENOC) to formalize commitments made by FENOC following the NRC staff's issuance of a Demand for Information (DFI) on May 14, 2007. The DFI was issued in response to the information provided by FENOC relative to its re-analysis of the time line and root causes for the 2002 Davis-Besse reactor pressure vessel head degradation event following its receipt of a report prepared by Exponent Failure Analysis Associates and Altran Solutions Corporation (Exponent). On June 13, 2007, FENOC provided its response to the DFI. On July 16, 2007, FENOC provided a supplemental response to the DFI which provided additional detail regarding the planned implementation of commitments established in its June 13, 2007, response to the DFI.